Changes to Traffic Management Acts
- Wednesday, March 26, 2008
Traffic Management - notice periods
The new Traffic Management Act (England & Wales) and Traffic Scotland Act will come into effect on 1st April 2008. The aim is to help manage traffic congestion more effectively by placing a Network Management duty on the Roads Authorities. The updated Acts also mean the notice period required is now dependant on:
|
Works duration (days)
|
Notice
|
|
|
England & Wales:
Based on works duration, not street sensitivity
|
Up to 3
Up to 10
Over 10
|
3 days
10 days
3 month advance notice
|
|
Scotland:
Based on combination of works duration and street sensitivity
|
Up to 10
Over 10
|
1 month advance (traffic sensitive) and 7 days (non traffic sensitive)
3 month advance notice
|
To minimise any inconvenience and possible delay to your schedule Core will determine the works duration of your project on receipt of an enquiry. If a 3 month advance notice is required we will contact you to discuss your development and the best way of applying prior to acceptance.